Project reference · Shanghai, China · 1.72 MW / 6.27 MWh
Shanghai Cable Manufacturing Energy Storage Project
The HUA-X group introduction records a 1.72 MW / 6.27 MWh electrochemical energy storage project reference for Shanghai Changshun Elevator Cable Co., Ltd. The project profile describes industrial electricity-cost management, time-of-use energy shifting and improved facility power-supply reliability as its principal objectives.
Published material shows HUA-X-branded energy storage cabinets. Exact equipment models, quantities, contractual responsibilities and dated delivery or commissioning milestones have not been publicly confirmed.

Project objectives
The project profile identifies three operating objectives for the cable-manufacturing facility:
- Manage production-related electricity costs.
- Shift electricity use between tariff periods.
- Improve facility power-supply reliability.
These are stated project objectives rather than verified operating results. The available source does not include the interval-load profile, tariff structure, dispatch schedule, protected-load arrangement or measured savings required to quantify financial or reliability performance.
System scale and configuration boundary
The published project scale is 1.72 MW / 6.27 MWh. These values describe the overall project reference but do not establish the AC or DC measurement point, usable AC energy, guaranteed discharge duration or end-of-life capacity.
The exact battery cabinet model, cabinet quantity, PCS configuration, EMS architecture, transformer and switchgear scope are not publicly disclosed.
Equipment and project status
The project photograph shows HUA-X-branded energy storage cabinets. HUA-X’s contractual role and the division of battery, PCS, EMS, installation and commissioning responsibilities are not publicly disclosed.
Delivery, installation, commissioning, customer-acceptance and commercial-operation dates are not publicly available.
Planning a comparable manufacturing project
Power and energy requirements for a manufacturing site depend on its load profile, tariffs, operating objectives and electrical connection. Relevant project information includes:
- At least 30 days of interval load data.
- Production schedule and planned load changes.
- Tariff periods, demand charges and export restrictions.
- Target grid-import or peak-demand limit.
- Required discharge duration and reserve.
- Critical or protected loads.
- Grid connection voltage and transformer capacity.
- Available installation space and environmental conditions.
- Battery, PCS, EMS, transformer and switchgear responsibilities.
- Installation, commissioning and acceptance requirements.
- Applicable local grid, fire-safety and electrical requirements.
Project FAQ
Questions about this project reference
Project status, equipment and energy-rating questions.
Was the project commissioned?
Which HUA-X products were used?
Does 6.27 MWh represent usable AC energy?
How can a similar manufacturing project be evaluated?
Plan a similar energy storage project
Planning industrial energy storage for a manufacturing facility?
Send your load profile, tariff structure, operating objective, site information and required project scope. HUA-X can review the appropriate power, energy duration and system boundary for a comparable proposal.
Response target: within 12 hours. Supply scope, documents, lead time and warranty are confirmed with the quotation.
